About the Arnold Field Turf Project

This summer, Lebanon Valley College's Arnold Field underwent a renovation that included the installation of a FieldTurf Revolution artificial turf field, track re-surfacing, competition-quality lighting, and other enhacements. The upgraded facility is home to LVC's football, field hockey, men's and women's lacrosse, and men's and women's track & field programs.

Lebanon Valley College partnered with industry leaders in athletic facility construction to ensure the very best finished product for its student-athletes. They included designer Activitas, which has worked with Harvard, Penn, Villanova, and the New England Patriots; Clark Companies, which has done hundreds of pro and collegiate athletic facility installations including the fields at MetLife Stadium and West Point's Michie Stadium; Musco, the global leader in sports lighting systems; and FieldTurf, the worldwide standard for artificial playing surfaces with more than 15,000 installations.
 

Construction Progress Photo Gallery

May 2012 Photos
June 2012 Photos
July 2012 Photos
August 2012 Photos
Turf Installation Photos

Arnold Field Project Timeline

Week of May 14 - Construction began
June 27 - Lights installed
Week of July 2 - Start of turf installation
Week of July 23 - Start of track re-surfacing
Mid-August - Facility completion and handover
Week of August 20 - Teams reported for camp, first practices on new field
Sept. 1 - First field hockey game on new turf, vs. Mary Washington
Sept. 8 - First football game on new turf, vs. Misericordia
Sept. 29 - First night game, field hockey vs. Messiah
 


Arnold Field Project News

Football Makes Arnold Field Turf Debut
Field Hockey Holds First Game On Turf
Football Holds First Practice At Field
FieldTurf Completed
FieldTurf Installation Begins

Project Announcement
Lights Announcement
Artist's Rendering